Sewerage & Drainage : Benefits from KEIIP work
Tranche 2 will continue improvements in coverage and operational sustainability of Kolkata Municipal Corporation's sewerage, drainage
Sewerage and drainage extension to peripheral areas continued: 91 km of additional sewer drainpipes constructed. The achievement includes 7.05 km of laying of pipes having size of over 1,000 mm diameter under contract packages SD-12 and SD-22 using micro-tunneling. One additional pumping station constructed and 3 being constructed against the target of five and 3.50 km of pumping main completed against the target of 6 km
 
                      Construction of Sewerage & Drainage Network in Thakurpara and Purba Putiary Catchment and Construction of Keorapukur PS in Ward-114, Borough XI including Operation & Maintenance of the Pumping Station
- Contractor
- M/s SNET JBPL JV
- Date of Commencement : 07.02.2017
- Revised completion date: 30.09.2022
- Revised Contract Amount (INRM): 834.38 (Works)+31.33 (O&M)
Main components
- S & D Network of different diameter- 37.0 Km. (approx.)
- Construction of 1 no. Pumping station
 
                      Construction of Sewerage & Drainage Network in Rania Box Catchment (Part of Ward Nos.111, 112 & 113) in Borough XI
- Contractor
- Simplex infrastructure Ltd.
- Date of Commencement : 18.10.2019
- Revised date of completion : Scheduled: 31.12.2024
- Expected date of completion : Scheduled: 31.05.2025
- Original Contract Amount (INR): 99.84
- Revised Contract Amount (INR): 118.21
Main components
i. S & D Network of different diameter- 12.0 Km. (approx.)
ii. Outfall structure 1 no. with provision of Sluice Gate
Status of components of work as on 31.01.2025
- Laying of S&D lines in Ward 111,112,113
- Scope:- 14.0 Km
- Completed as on 31.01.25: 12.18 km
- Balance as on 31.01.25: 1.82 km
- House Drainage connections
- Scope:- 1056 Nos
- Completed as on 31.01.25: 664 Nos.
- Balance as on 31.01.25: 392 Nos.
- Laying of MS pipe
- Scope:- 650 m
- Completed as on 31.01.25: 435 m
- Balance as on 31.01.25: 215 m
 
                      Construction of Sewerage & Drainage Network in Vivekananda Road Catchment (Part of Ward Nos.113 & 114) and Construction of a Pumping Station in Borough XI including Operation & Maintenance of the Pumping Station
- Contractor
- Simplex infrastructure Ltd.
- Date of Commencement : 20.11.2019
- Revised date of completion 30.09.2024 for PS WOrks and 31.12.2024 for network + O & M period (5 Yrs)
- Expected date of completion 31.03.2025 + O & M period (5 Yrs)
- Revised Contract Amount (INR): 125.21 (Works) + 2.58 (O&M)
- Revised Contract Amount (INR): 120.08(Works) + 2.58 (O&M)
Main components
- S & D Network of different diameter- 10.0 Km. (approx.)
- Outfall structure 6 nos. with provision of Flap Gate
- SWF Pumping main 1200 mm diameter - 2.2 Km
- Construction of Vivekananda Road Pumping Station
Status of components of work as on 31.01.2025
- Laying of sewer in Ward113,114
- Scope:- 10.526 Km
- Completed as on 31.01.25: 10.350 km
- Balance as on 31.01.25: 0.176 km
- Laying of 1200 mm MS Pumping Main
- Scope:- 0.9 km
- Completed as on 31.01.25: 0.9 Km
- Balance as on 31.01.25: 0.0 Km
- Laying of 700 mm DI Pumping Main
- Scope:- 0.81 Km
- Completed as on 31.01.25: 0.2 Km
- Balance as on 31.01.25: 0.61 Km
- Pumping Station
- Completed as on 31.01.25: 93.6% completed, SWF pump put into partial operation
- House Drainage Connections
- Scope:- 814 Nos.
- Completed as on 31.01.25: 753 Nos
- Balance as on 31.01.25: 61 Nos.
 
                      Laying of Trunk Sewer along James Long Sarani by Micro-Tunneling Method
- Contractor
- M/s ITD-ITD CEM Joint Venture
- Date of Commencement : 08.02.2017
- Work completed and Final inspection date & handing over date: 31.10.2020
- Revised Contract Amount (INRM):1152.36 (Works)
Main components
i. Laying of Trunk Sewer by Micro-Tunneling method along Diamond Harbour Road about 3.8 Km
 
                      Development of Sewerage and Drainage Network within James Long Sarani& Mahatma Gandhi Road Catchment in Borough XVI (Part of Ward No. 123 & 124)
- Contractor
- Simplex Infrastructures Ltd.
- Date of Commencement : 05.12.2016
- Revised completion date: 31.08.2024
- Expected date of completion: 28.02.2025
- Revised Contract Amount (INRM): 742.64 (Works)
Main components
i. S & D Network of different diameter- 15.3 Km. (approx.)
Status of components of work as on 31.01.2025
- Laying of Sewers in Wards 123&124
- Scope:- 12.387 Km
- Completed as on 31.01.25: 12.387 Km
- Balance as on 31.01.25: 0 km
- House Drainage Connections
- Scope:- 1670 Nos
- Completed as on 31.01.25: 1650 Nos
- Balance as on 31.01.25: 20 Nos.
 
                      Laying of Lateral Sewers in part of Borough XIV (Ward Nos. 128 to 132) and De-siltation of Box Drain at Picnic Garden Road
- Contractor
- Simplex Infrastructures Ltd.d
- Date of Commencement : 05.12.2016
- Work completed on 31.08.2021
- Revised Contract Amount (INRM): 1382.59 (Works)
Main components
- S & D Network of different diameter- 53.4 Km. (approx.)
- De-silting of box drain at Picnic Garden Road
 
                      Sewerage and Drainage Mains and 2 Pumping Stations (Augmentation of Keorapukur MPS) in Tolly Nullah/ Keorapukur Sub-Basin in Borough-XIII (Ward No. 115 & Part of Ward No. 122)
- Contractor
- Simplex Infrastructures Ltd
- Date of Commencement : 18.09.2017
- Revised completion date: 31.12.2024
- Call for Termination
- Revised Contract Amount (INR): 79.55 (Work) & 2.60 (O&M) for PS ( 5 years)
- Revised Contract Amount (INR): 84.94 (Work) & 2.60 (O&M) for PS ( 5 years
Main components
- Development of trunk S&D network – 8.8 km
- Construction of SWF pumping station – Kudghat drainage PS (4 nos. of SWF pump, each having capacity 800 lps)
- Augmentation of Keorapukur MPS at Dhalipara (installation of 2 nos. of pumps, each having capacity 650 lps)
- Desilting of existing Sewers along MG Road & Banerjee Para Road
- Laying of MS pumping main of 1200 mm diameter – 600 m Construction of outfalls
Status of components of work as on 31.01.2025
- Laying of sewer in Ward 115 &122
- Scope:- 9.0 Km
- Completed as on 31.01.25: 7.93 Km
- Balance as on 31.01.25: 1.077 Km
- Pumping Main
- Scope:- 0.25Km
- Completed as on 31.01.25: 0.25 Km
- Balance as on 31.01.25: 0.0 km.
- Pumping Station
- Keorapukur MPS: - Commissioning & completed
- Kudghat PS :- 95% completed
- HDC
- Scope:- 1055 Nos
- Completed as on 31.01.25: 997 Nos
- Balance as on 31.01.25: 58 Nos.
 
                      Development of S&D Network in Churial Extension Canal Sub-basin in Borough XIII & XVI (Part of Ward 122, 123, 124) including laying of main trunk sewer by Micro-tunnelling method and construction of Churial Extension Pumping Station
- Contractor
- M/s ITD-ITD CEM Joint Venture
- Date of Commencement : 04.06.2018
- Revised date of completion : 31.08.23+ O & M period (5 Yrs)
- Expected date of completion : 31.05.2025 + O & M period (5 Yrs)
- Revised Contract Amount (INR): 294.31 (Work) & 1.84 (O&M) for PS ( 5 years)
- Revised Contract Amount (INR): 410.11 (Work) & 1.84 (O&M) for PS ( 5 years)
Main components
- Development of S&D Network.
- Laying of main Trunk Sewer by Micro tunnelling Method
- Construction of pumping station
Status of components of work as on 31.01.2025
- Laying of sewer lines
- Scope:- 21.8 Km
- Completed as on 31.01.25: 20.5 Km
- Balance as on 31.01.25: 1.3 km
- Pumping Main
- Scope:- 2.4 Km
- Completed as on 31.01.25: 2.4 Km
- Balance as on 31.01.25: 0.0 km.
- Pumping Station
- Completed & Commissioned
- HDC
- Scope:- 1742 Nos
- Completed as on 31.01.25: 1652 Nos
- Balance as on 31.01.25: 90 nos.
* The above mentioned progress has been updated till 28th February, 2025.


