Sewerage & Drainage Benefits from KEIIP work

Tranche 3 - Status of Implementation Progress*

Tranche 3 will continue expanding sewerage and drainage services in selected peripheral areas of Kolkata Municipal Corporation (KMC) to at least 3,000 additional households and provide sewage treatment for at least 100,000 households covered under Kolkata Environmental Improvement Investment Program. It will construct (i) at least 43 km of additional sewer drain pipes; (ii) four pumping stations and at least 13 km of pumping mains and one existing pumping station upgraded; and (iii) three sewage treatment plants, with at least 115 million liters per day combined capacity.

Improvement of S&D network and construction of pumping station in Alipore body guard line premises in Ward 74

  • Contractor
  • RG - Jyoti JV
  • Date of Commencement : 20.11.2019
  • Date of completion 18.11.2021+ O & M period (05 yrs.)
  • Contract Amount (INRM): 395.92 (Works)+ 20.03 (O & M)
Physical Progress
19.45%

Main Components

  • Development of S&D Network within BGL campus, ward 74-3.0 km
  • Construction of Combined Cycle Pumping Station within BGL campus-SWF-3 working + 1 standby + 1 future, capacity 300 lps each, DWF-2 working + 2 standby, capacity 16 lps each
  • Laying of SWF Pumping Main (1016 mm outer diameter) through National Library Avenue and Belvedere Road-1.2 km (Part to be laid by Micro tunneling method for 0.3 km and part to be laid by cut and cover method for 0.85 km and part to be laid by Jack pushing method for 0.05 km) and laying of DWF pumping main (200 mm dia.)-30 m

Construction of Sewage Treatment Plant near WBSETCL, Joka

  • Contractor
  • M/s SNET-SSG JV
  • Date of Commencement : 08.03.2019
  • Date of completion 02.09.2021+ O & M period (05 yrs.)
  • Contract Amount (INRM): 781.71 (Works)+ 43.49 (O & M)
Physical Progress
13.82%

Main components

  • The proposed STP will cater to the DWF generated from wards 125, 126, 144 and parts of ward 123, 124 and 143 under Borough XVI and 127 (Borough XIV). The population of the catchment for the design horizon (2030) is 2,57,882 and its total catchment is approximately 1444 Ha, which will serve as the command area for the proposed STP.
  • The site of the proposed STP is located off the Diamond Harbour Road in ward no. 144 in South Kolkata primarily identified as Joka, the complete command area of the WBSETCL STP

Construction of Sewage Treatment Plant at Bank Plot, MG Road, Joka

  • Contractor
  • M/s SNET-EAGLE INFRA JV
  • Date of Commencement : 08.03.2019
  • Date of completion 02.09.2021+ O & M period (05 yrs.)
  • Contract Amount (INRM): 703.14 (Works) + 41.53 (O & M)
Physical Progress
10.97%

Main components

The site of the proposed STP is located off Mahatma Gandhi Road in ward no. 143 of KMC in South Kolkata; the land parcel is identified as Bank Plot.

Construction of 23 MLD sewage treatment plant at Rajpur- Sonarpur, Rania including O & M for 15 years

  • Contractor
  • M/s TEPL- SNET JV
  • Date of Commencement : Contract Signed and N.T.P yet to be issued
  • Date of completion 21 months (work)+ 180 months (O & M)
  • Contract Amount (INRM): 632.74 (Works)+ 55.26 (O&M)
Physical Progress
Nil

Status

Contract Signed and N.T.P yet to be issued

Development of S&D Network in Churial Extension PS catchment & Diamond Park catchment and construction of Churial Extension pumping station (Annex) in Borough XVI (Part of Ward 124, 143 & 144)

  • Contractor
  • Simplex Infrastructures Ltd
  • Date of Commencement : 18.10.2019
  • Date of completion: 16.10.2022 (work)+ O & M period (5 yrs)
  • Contract Amount (INRM): 1131.38 (Works)+28.00(O & M)
Physical Progress
12.79%

Main components

  • S & D Network
  • Supply & laying of RCC NP3 Pipe dia. range 300 mm-2000 mm
  • Supply & laying of RCC NP4 Pipe (Jack pushing) dia. range 1200 mm-2000 mm
  • Supply and laying of MS pipe 1400 mm
  • Manhole Construction
  • HD connection IP/GP/CP
  • Road work upto jhama

  • Churial Pumping Station
  • Well Foundation
  • Substation building

Development of S & D network in Bakrahat Road catchment (Ward 125) and laying of RCC sewer line along Bakrahat Road and D.H.Road by Micro tunnelling and Cut & Cover method.

  • Contractor:
  • ATOZ ADHUNIK JV
  • Date of Commencement :N.T.P. issued on 04.01.2021
  • Date of completion: Scheduled:03.01.2023
  • Contract Amount (INRM): 485.10
Physical Progress
Nil

Main Components

Development of S & D network in Bakrahat road catchment (Ward 125) by cut & cover method and laying of RCC sewer line along Bakrahat road and D.H. Road by Micro-tunnelling

Improvement of S&D system in Mukundapur Area (Part of Ward 109) including construction of pumping station

  • Contractor:
  • M/s Laxmi- WM JV
  • Date of Commencement :N.T.P yet to be issued
  • Date of completion: 24 months (work)+ 60 months (O & M)
  • Contract Amount (INRM): 1487.75 (Works)+ 26.94 (O&M)
Physical Progress
Nil

Status

Contract signed and N.T.P yet to be issued

Construction of 2 new Pumping Stations near Lalababu Nikashi and Bagjola Canal and within Behala Node C Premises, Sakuntala Park

  • Contractor
  • Ramky Infrastructures Ltd.
  • Date of Commencement : 29.11.2019
  • Date of completion: 27.11.2021(work)+ O & M period (5 yrs)
  • Contract Amount (INRM): 584.13 (Works)+ 88.13(O & M)
Physical Progress
9.17%

Main components

  • Construction of pumping station at confluence of Lala babu Nikashi & Bagjola canal, South Dum Dum Municipality Part of Borough I (Ward 3, 4, 5) and part of South Dumdum municipality are covered under the specific PS Subproject. Total catchment is 230 Ha approximately
  • Construction of new pumping station in the premises of Node C, Sukuntala Park, Behala After Demolishing of Existing Infrastructure Pumping station shall be constructed in the premises of Node C, Sukuntala Park, Behala. There is an existing DWF pumping station in the said premises. The pumping station was constructed under Ganga Action Plan. The sewerage and drainage (S &D) works in the catchment area of the pumping station have already been implemented and system is functioning. The new pumping station is proposed to be constructed by dismantling the existing PS including the annular sump, dry pit and pump house superstructure

* The above mentioned progress has been updated till 31st March 2021.