Sewerage & Drainage : Benefits from KEIIP work
Tranche 2 will continue improvements in coverage and operational sustainability of Kolkata Municipal Corporation's sewerage, drainage
Out of 8 awarded sewerage and drainage contracts, 2 contracts terminated. Balance works of terminated contracts were bid out and awarded. Presently works ongoing for all the 8 contracts.

Construction of Sewerage & Drainage Network in Thakurpara and Purba Putiary Catchment and Construction of Keorapukur PS in Ward-114, Borough XI including Operation & Maintenance of the Pumping Station
- Contractor
- M/s SNET JBPL JV
- Date of Commencement : 07.02.2017
- Revised date of completion 31.05.2020
- Revised Contract Amount (INRM): 834.38 (Works)
Physical Progress
Main components
- S & D Network of different diameter- 37.0 Km. (approx.)
- Construction of 1 no. Pumping station

Construction of Sewerage & Drainage Network in Rania Box Catchment (Part of Ward Nos.111, 112 & 113) in Borough XI
- Contractor
- Simplex infrastructure Ltd.
- Date of Commencement : 18.10.2019
- Revised date of completion : Scheduled: 16.10.2022
- Revised Contract Amount (INRM): 998.35
Physical Progress
Main components
i. S & D Network of different diameter- 12.0 Km. (approx.)
ii. Outfall structure 1 no. with provision of Sluice Gate

Construction of Sewerage & Drainage Network in Vivekananda Road Catchment (Part of Ward Nos.113 & 114) and Construction of a Pumping Station in Borough XI including Operation & Maintenance of the Pumping Station
- Contractor
- Simplex infrastructure Ltd.
- Date of Commencement : 20.11.2019
- Revised date of completion 18.11.2022 + O & M period (5 Yrs)
- Revised Contract Amount (INRM): 1252.12 (Works) + 25.77 (O&M)
Physical Progress
Main components
- S & D Network of different diameter- 10.0 Km. (approx.)
- Outfall structure 6 nos. with provision of Flap Gate
- SWF Pumping main 1200 mm diameter - 2.2 Km
- Construction of Vivekananda Road Pumping Station

Laying of Trunk Sewer along James Long Sarani by Micro-Tunneling Method
- Contractor
- M/s ITD-ITD CEM Joint Venture
- Date of Commencement : 08.02.2017
- Revised date of completion: Rev. Comp. Dt. (no of ext.)15.10.2020(1)
- Revised Contract Amount (INRM):1152.36 (Works)
Physical Progress
Main components
i. Laying of Trunk Sewer by Micro-Tunneling method along Diamond Harbour Road about 3.8 Km

Development of Sewerage and Drainage Network within James Long Sarani& Mahatma Gandhi Road Catchment in Borough XVI (Part of Ward No. 123 & 124)
- Contractor
- Simplex Infrastructures Ltd.
- Date of Commencement : 05.12.2016
- Revised date of completion : 31.12.2020
- Revised Contract Amount (INRM): 742.64 (Works)
Physical Progress
Main components
i. S & D Network of different diameter- 15.3 Km. (approx.)

Laying of Lateral Sewers in part of Borough XIV (Ward Nos. 128 to 132) and De-siltation of Box Drain at Picnic Garden Road
- Contractor
- Simplex Infrastructures Ltd.d
- Date of Commencement : 05.12.2016
- Revised date of completion 17.01.2021
- Revised Contract Amount (INRM): 1382.59 (Works)
Physical Progress
Main components
- S & D Network of different diameter- 53.4 Km. (approx.)
- De-silting of box drain at Picnic Garden Road

Sewerage and Drainage Mains and 2 Pumping Stations (Augmentation of Keorapukur MPS) in Tolly Nullah/ Keorapukur Sub-Basin in Borough-XIII (Ward No. 115 & Part of Ward No. 122)
- Contractor
- Simplex Infrastructures Ltd
- Date of Commencement : 18.09.2017
- Revised date of completion: 17.09.2020 + O & M period (5 Yrs)
- Revised Contract Amount (INRM): 852.08 (Works) +26.00 (O&M)
Physical Progress
Main components
- Development of trunk S&D network – 8.8 km
- Construction of SWF pumping station – Kudghat drainage PS (4 nos. of SWF pump, each having capacity 800 lps)
- Augmentation of Keorapukur MPS at Dhalipara (installation of 2 nos. of pumps, each having capacity 650 lps)
- Desilting of existing Sewers along MG Road & Banerjee Para Road
- Laying of MS pumping main of 1200 mm diameter – 600 m Construction of outfalls

Development of S&D Network in Churial Extension Canal Sub-basin in Borough XIII & XVI (Part of Ward 122, 123, 124) including laying of main trunk sewer by Micro-tunnelling method and construction of Churial Extension Pumping Station
- Contractor
- M/s ITD-ITD CEM Joint Venture
- Date of Commencement : 04.06.2018
- Revised date of completion : 02.06.2021+ O & M period (5 Yrs)
- Revised Contract Amount (INRM): 3149.78 (Works)+ 18.46(O&M)
Physical Progress
Main components
- Development of S&D Network.
- Laying of main Trunk Sewer by Micro tunnelling Method
- Construction of pumping station
* The above mentioned progress has been updated till 28th February 2021.