Water Supply-Benefits from KEIIP work
Tranche 2 will continue improvements in coverage and operational sustainability of Kolkata Municipal Corporation's water supply services
In progress. 8 water supply contracts awarded and works ongoing. 9 service reservoirs are physically completed and 2 service reservoirs work ongoing. 27 km of transmission mains and 263 km of distribution mains are rehabilitated/constructed. 11600 water meters installed.
Construction of Underground Reservoirs and Overhead Reservoirs, Pumping Stations and Linking Pumping Station Main for Water Supply in Joka and Adjoining Areas including Operation and Maintenance of the Pumping Stations
- Contractor
- Gannon Dunkerley & Company Ltd
- Date of Commencement : 05.12.2016
- Revised completion date: 15.09.2022
- Revised Contract Amount (INRM): 1109.40(Works)+ 40.95(O&M)
Main components
- Construction of 2 Nos. Underground Reservoirs with Pump House
- ii. Construction of 6 Nos. Elevated Service Reservoirs
Laying of Transmission Main from Daspara PS to UGRs at Prantik PH=III, KMC Land on Julpia Road and Transmission Main from PS to zonal Reservoir
- Contractor
- FFIL-RIL JV
- Date of Commencement : 19.05.2017
- Revised completion date: 30.06.2022
- Revised Contract Amount (INRM): 559.23 (Works)+ NA(O&M)
Main components
i. Laying of Transmission Main from Dapara PS to UGRs
ii. Transmission Main from PS to zonal Reservoir
Laying of Water Supply Distribution Network Including Providing Household Service Connection in 4 Distribution Areas in Joka and Adjoining Areas for the Command Area under proposed ESRs at Prantik Ph III, N-E of SSE STP and N-W of SSE STP and Existing ESR at Prantik.
- Contractor
- Simplex Infrastructures Ltd
- Date of Commencement : 17.06.2017
- Revised completion date: 30.10.2022
- Revised Contract Amount (INRM): 1112.84(Works)+ NA (O&M)
Main components
Laying of Water Supply Distribution Network Including Providing Household Service Connection in 4 Distribution Areas in Joka and Adjoining Areas for the Command Area under proposed ESRs at Prantik Ph III, N-E of SSE STP and N-W of SSE STP and Existing ESR at Prantik
Laying of Water Supply Distribution Network Including Providing Household Service Connection in 4 Distribution Areas in Joka and Adjoining Areas for the Command Area under proposed ESRs at Company Pukur, WBSETCL and 22 Bigha and Existing ESR at Diamond Park
- Contractor
- Simplex Infrastructures Ltd
- Date of Commencement : 17.06.2017
- Revised completion date: 30.10.2022
- Revised Contract Amount (INRM): 991.84(Works)+ NA(O&M)
Main components
Laying of Water Supply Distribution Network Including Providing Household Service Connection in 4 Distribution Areas in Joka and Adjoining Areas for the Command Area under proposed ESRs at Company Pukur, WBSETCL and 22 Bigha and Existing ESR at Diamond Park
Laying of Transmission Main from pumping station to proposed 3 ESRs at Ramkantapur, Malpara, Charaktala & Construction of the 3 ESRs including laying of distribution Network with House Service Connection within the command area of the 3 ESRs for water supply in Joka and adjoining areas.
- Contractor
- FFIL-RIL JV
- Date of Commencement : 15.05.2017
- Revised completion date: 30.11.2021
- Revised Contract Amount (INRM): 962.55 (Works)+ 12.63 (O&M)
Main components
i. Construction of 3 nos. ESR
ii. Transmission Main from UGR at KMC Land on Julpia Road to 3 ESRs
iii. Distribution System and House Connection within Command Area of 3 ESRs
Dedicated Water Supply Transmission Main from Junction of James Long Sarani to Daspara near existing Pumping Station along James Long Sarani.
- Contractor
- Simplex Infrastructures Ltd
- Date of Commencement : 26.10.2017
- Work completed. Final inspection and handing over date is 12.03.2022.
- Revised Contract Amount (INRM): 627.56(Works)+ NA (O&M)
Main components
i. Water Supply Transmission Main from Junction of James Long Sarani to Daspara
Performance Based Contract for Water Loss Management in Anandapur Area and Patuli Area under Jai Hind WTP (Eastern Kolkata)
- Contractor
- Suez India Pvt. Ltd
- Date of Commencement : 04.10.2018
- Revised completion date: 31.08.23+ O & M period (3 Yrs)
- Revised Contract Amount (INRM): 1316.31 (Works) + 472.99 (O&M)
Main components
i. Topographical survey including customer survey for updating water supply service connection database.
ii. Review of existing WS distribution network and preparing of District Metered Areas within the command zones.
iii. Supply and Laying of WS distribution network.
iv. Supply and installation of flow meters including data logging.
v. Conducting Leak Detection and carrying out pipeline repairs at leakage points.
vi. Providing and installing Household service connection.
vii. Installation of Domestic Water Meters including taking meter readings.
viii. Operation and Maintenance of the District Metered Areas (DMAs) including flow recording, monitoring and assessment of water loss on a regular basis.
Water Supply System Instrumentation and Information Technology Upgrade
- Contractor
- HITECH-SHANTA COLIBRI JV
- Date of Commencement : 05.03.2019
- Revised completion date:31.08.2021
- Revised Contract Amount (INRM): 163.74 (Works) + 5.00 (O&M)
Main components
i. Water Supply System Instrumentation and Information Technology Upgrade in total KMC area
Work completed and final inspection date is on 31.08.2021 and handed over on 26.10.2021
Augmentation of Storage capacity and transmission main under Jai Hind WTP-clear water reservoir, service main and electromechanical works
- Contractor
- TEPL-SNET JV
- Date of Commencement : 24.09.2018
- Schedule date of Completion: 22.09.2020
- Revised Contract Amount (INRM): 466.50 (Works)+ NA(O&M)
Main components
i. Jai Hind Water works
a) Supply & Installation of new pumping unit at Raw Water Pumping Station - One (1) set of Raw Water pump and pumping units of 3181.50 Cu-m/hr. capacity @ 16 m head with 220 KW motor. Contractor shall supply & Install new units with mentioned technical specifications, data and performance.
b) Supply & Installation of New of Clear Water Pumping unit at Clear Water Pumping Station -One (1) set of Clear Water Pump and pumping units of 7000 Cum/hr. capacity @ 45 m head with 1200 KW motor. Contractor shall supply and install new unit with mentioned technical specifications, data and performance. It shall be installed at the location of backwash pump as shown in the drawing.
c) Installation of Backwash pumping unit at suitable location of Clear Water Pumping Station -One (1) No Back Wash Pump will be relocated as shown in the drawing.
ii. Patuli Head Works
a) Supply & Installation of New Clear Water Pumping unit at Clear Water Pumping Station -One (1) set of Clear Water Pump and pumping units of 3000 Cum/hr. capacity @ 41 m head with 500 KW motor. Contractor shall supply and install new units with mentioned technical specifications, data and performance.
Work completed and final inspection and handed over on 31.12.2021.
Construction of Pumping Station to handle Sludge Water of Garden Reach Water Works (GRWW).
- Contractor
- GBC Infrastructure Limited
- Date of Commencement : 23.12.2020
- Revised completion date: 31.01.23 + O&M period (3 Yrs.)
- Contract Amount (INRM): 103.34 (Works) + 3.75 (O&M)
Main components
Construction of Pumping Station to handle Sludge Water of Garden Reach Water Works (GRWW).
Performance based water loss management works at Cossipore service zone, Ward no. 1 to 6
- Contractor
- >M/s Suez India Pvt. Ltd
- Date of Commencement : 23.12.2020
- Revised completion date:31.01.2023+ O&M period (5 Yrs.)
- Revised Contract Amount (INRM): 769.7 (Works)+ 178.4 (O&M)
Main components
i. Establishment of District Water Meter Areas in ward numbers 1 to 6
ii. Providing DI k9 grade pipes between 100mm to 700mm diameter
iii. Providing and supplying Polyethylene Pipes of assorted diameters
iv. Supply and installation of various types of valves of assorted diameters
v. Supply and Installation of Domestic Water Meter and Bulk Meters of assorted diameters.
vi. Water loss reduction (NRW) and management services and Operation and Maintenance for a period of 3 years
* The above mentioned progress has been updated as per progress till 30th March 2023.